Update: Beginning May 21, 2024 the Cathcart Boulevard entrance to Canatara Park will be closed for resurfacing. Work is expected to be complete by May 25. Please use the Sandy Lane entrance on the west side of the park for access. Immediately following the reopening of the Cathcart Boulevard entrance, Lake Chipican Drive will be closed from Cathcart Boulevard to the centre beach parking lot entrance. Access for residents in the area will be maintained. |
March 27, 2024 — Work will commence in early April on road and path resurfacing in Canatara Park.
Project scope
The $839,236 project will include:
- Resurfacing of Animal Farm Road and parking lots
- Resurfacing of portions of Lake Chipican Drive
- Resurfacing of the Park Service Road
- Resurfacing of Charlesworth Lane
- Resurfacing of Andover Lane
- Pathway resurfacing
Project map
Consult the map below to see the full project area highlighted in red. Resurfacing will be completed in phases.
Project impacts
Drivers should expect shifting road closures in the park as work is completed. Areas of the park will intermittently be impacted by construction activities.
Project timeline
The project is expected to begin the first week of April 2024, dependent on weather and contractor mobilization. Work is targeted for completion in summer 2024.
Project area
The project will include the areas of:
- Lake Chipican Drive from Christina Street North to the eastern park roundabout
- Charlesworth and Andover Lanes
- The Park Service Road
- Animal Farm Road and parking lots